Methods/Steps
1. PE pipe clamp is fixed and aligned
2. End face milling of PE pipe
3. End face melting of PE pipe
4. PE pipe butt fusion welding
5. PE pipe cooling and then pipe welding are completed
PE pipes shall be visually inspected after connection, and those unqualified shall be reworked immediately. After passing the test, the next pipe welding can be carried out.